The ferry terminal’s up-march area for cars and trucks is being renovated on an area equivalent to 50,000 m2.
Existing lanes are being broken up and materials that cannot be reinstated are being disposed of.
New areas are being put into use to increase the total number of lane meters.
New base construction, curbs and asphalt paving are being carried out. Existing sewers and drainage are being
partially replaced.
The area is being provided with a new signal system for road users, new light poles, as well as fences and gates
The work will be carried out in 2023 and 2024.
Order size:
DKK 37 million
Contractor:
Depenbrock Scandinavia ApS
Contract:
Main Contractor
Client:
Scandlines Danmark ApS
Construction period:
01.03.2023 – 15.06.2024
Location:
Rødby, Denmark
Technical specifications and quantities:
• Demolition of existing asphalt: 21030 m2
• New roadbed construction: 10300 m2
• New curbs 3800 m
• New Gutter Manholes Ø315: 66 pcs.
• New rainwater pipe Ø800: 150 m
• New GAB II asphalt: 21030 m2
• New ABB and SMA asphalt: 46340 m2
• New light masts 38 pcs.